At riskNext-Gen Infusion Pump
Jan 15, 2026 → Nov 30, 2026 3 team members
Phase 1
Design & Engineering
Phase 2
Manufacture & Assembly
Phase 3
Quality & Support
Progress
62%
SPI
0.91
≥ 0.95 healthy
CPI
0.94
≥ 0.95 healthy
Quality
88
≥ 85 healthy
Benchmark grading
Product PM (PMI/ISO 21500)
At riskCommercial product portfolios tolerate moderate schedule and cost variance as long as scope and quality are protected. Bands reflect typical earned-value reporting in hardware and firmware programs.
Schedule (SPI)0.91 / ≥ 0.95
Cost (CPI)0.94 / ≥ 0.95
Quality88 / ≥ 85
Open critical defects1 / ≤ 0
Source: PMI PMBOK 7 · ISO 21500
Top AI insights
AI generated
Schedule · AI
IEC 60601 testing likely to slip 2–3 weeks
Pilot run completion is trending 9 days late and feeds directly into safety testing. Probability of milestone slip: 78%.
Cost · AI
Predicted EAC $110K over budget
BOM components and tooling both ran 5–10% over plan. Projecting final cost at $1.96M vs $1.85M budget.
Quality · AI
Firmware defects cluster around alarm subsystem
3 of last 5 defects (incl. 1 critical) trace to alarm/event handling. Recommend dedicated code review before next pilot run.