Nordic Telecom
Telecom & Office Equipment
DelayedFiber ONU Refresh
Aug 1, 2025 → Aug 15, 2026 2 team members
Phase 1
Design & Engineering
Phase 2
Manufacture & Assembly
Phase 3
Quality & Support
Progress
84%
SPI
0.82
≥ 0.95 healthy
CPI
0.96
≥ 0.95 healthy
Quality
79
≥ 85 healthy
Benchmark grading
Product PM (PMI/ISO 21500)
DelayedCommercial product portfolios tolerate moderate schedule and cost variance as long as scope and quality are protected. Bands reflect typical earned-value reporting in hardware and firmware programs.
Schedule (SPI)0.82 / ≥ 0.95
Cost (CPI)0.96 / ≥ 0.95
Quality79 / ≥ 85
Open critical defects1 / ≤ 0
Source: PMI PMBOK 7 · ISO 21500
Top AI insights
AI generated
Schedule · AI
Interop testing 3 weeks behind
Critical defect D-201 blocks 40% of the test plan. SPI dropped to 0.82.
Quality · AI
Interop failures concentrate on Vendor X OLTs
All 4 fails this week involve the same OLT family. Suggest direct engagement with vendor before re-test.
Team
EH
Erik Hansen
Customer Lead
MK
Maya Kowalski
PM