AIKm PM
Nordic Telecom
Telecom & Office Equipment
Delayed

Fiber ONU Refresh

Aug 1, 2025Aug 15, 2026 2 team members

Phase 1
Design & Engineering
Phase 2
Manufacture & Assembly
Phase 3
Quality & Support
Progress
84%
SPI
0.82
≥ 0.95 healthy
CPI
0.96
≥ 0.95 healthy
Quality
79
≥ 85 healthy

Benchmark grading

Product PM (PMI/ISO 21500)
Delayed

Commercial product portfolios tolerate moderate schedule and cost variance as long as scope and quality are protected. Bands reflect typical earned-value reporting in hardware and firmware programs.

Schedule (SPI)0.82 / 0.95
Cost (CPI)0.96 / 0.95
Quality79 / 85
Open critical defects1 / 0

Source: PMI PMBOK 7 · ISO 21500

Top AI insights

AI generated
Schedule · AI

Interop testing 3 weeks behind

Critical defect D-201 blocks 40% of the test plan. SPI dropped to 0.82.

Quality · AI

Interop failures concentrate on Vendor X OLTs

All 4 fails this week involve the same OLT family. Suggest direct engagement with vendor before re-test.

Team

EH
Erik Hansen
Customer Lead
MK
Maya Kowalski
PM