OfficeWise
Telecom & Office Equipment
At riskMultifunction Printer X90
Dec 1, 2025 → Nov 15, 2026 2 team members
Phase 1
Design & Engineering
Phase 2
Manufacture & Assembly
Phase 3
Quality & Support
Progress
58%
SPI
0.93
≥ 0.95 healthy
CPI
0.97
≥ 0.95 healthy
Quality
84
≥ 85 healthy
Benchmark grading
Product PM (PMI/ISO 21500)
At riskCommercial product portfolios tolerate moderate schedule and cost variance as long as scope and quality are protected. Bands reflect typical earned-value reporting in hardware and firmware programs.
Schedule (SPI)0.93 / ≥ 0.95
Cost (CPI)0.97 / ≥ 0.95
Quality84 / ≥ 85
Open critical defects0 / ≤ 0
Source: PMI PMBOK 7 · ISO 21500
Top AI insights
AI generated
Schedule · AI
Pilot run delayed by paper-path issue
Jam defect at high speed risks pushing certification by ~10 days.
Quality · AI
Mechanical defects dominate
5 of last 6 defects are mechanical. Suggest a focused tolerance review with tooling vendor.
Team
YT
Yuki Tanaka
Customer Lead
KS
Kenji Sato
PM